Effort and Time Schedule

Defines when to carry out specific tasks and the involved effort to carry out these tasks.

Coarse Grained Schedule

The following tables are based on the instantiated activities of the detailed Project Schedule in section Procedure Organization and ties down the belonging plan specification.

Effort and Deadlines

PhaseActivity
Effort
Start
End
MS0: Project Start
18.10.04
InitialisationSet up workplace08:00h 18.10.0418.10.04
Set up project infrastructure16:00h18.10.0419.10.04
Configuration description08:00h19.10.0419.10.04
Define system requirements (doc)24:00h20.10.0421.10.04
Define project schedule24:00h21.10.0422.10.04
MS1: Release phase 'Concept'
25.10.04
ConceptEvaluation Software, Tools, Other Engines16:00h 25.10.04 25.10.04
System & Engine Architecture64:00h 26.10.04 29.10.04
Solution Description (detailed)80:00h 01.11.0405.11.04
MS2: Release phase 'Implementation'
08.11.04
ImplementationImplementation BPEL Model in Java32:00h 08.11.04 09.11.04
XML to Java Mapping 48:00h 10.11.04 12.11.04
Axis Integration 64:00h 15.11.04 18.11.04
System Integration 32:00h 19.11.04 22.11.04
Process Controller Logic 32:00h 23.11.04 24.11.04
Persistence16:00h 25.11.04 25.11.04
Demo16:00h 26.11.04 26.11.04
Custom Ant Tasks 16:00h 29.11.04 29.11.04
Testing32:00h 30.11.04 01.12.04
Documentation32:00h 02.12.04 03.12.04
MS3: Release bexee-0.1
06.12.04
MS4: Release phase 'Completion'
06.12.04
CompletionInstallation Manual
08:00
06.12.04
06.12.04
User Manual
08:00
06.12.04
07.12.04
Web Site / Docu review
48:00
07.12.04
09.12.04
Final Report
16:00
10.12.04
10.12.04
MS5: Project Closing
10.12.04

Effort Per Phase

Phase
Hours
Initialisation
80:00
Concept
160:00
Implementation
320:00
Conclusion
80:00
Total Effort
640:00

Milestones

The following milestones have been established for the bexee project:

MSMilestoneDate
MS0Project Start
18.10.04
MS1Release phase 'Concept'
25.10.04
MS2Release phase 'Implementation'
08.11.04
MS3Release bexee-0.1
06.12.04
MS4Release phase 'Completion'
06.12.04
MS5Project Closing
10.12.04

Delivery dates

This section lists the deliverables and makes a note of their target and actual state.

Initialisation

Deliverable
Target Date
Actual Date
Status
Project Schedule
22.10.04
22.10.04
Completed
Requirements Specification
22.10.04
22.10.04
Completed
Configuration Description
20.10.04
22.10.04
Completed

Concept

Deliverable
Target Date
Actual Date
Status
System & Software Architecture
01.11.04
05.11.04
Completed
Solution Description (detailed)
04.11.04
05.11.04
Completed

Implementation

Deliverable
Target Date
Actual Date
Status
bexee 0.1
15.11.04
12.11.04
Completed

Closing

Deliverable
Target Date
Actual Date
Status
Installation Manual 06.12.04 09.12.04
Completed
User Manual 07.12.04 09.12.04
Completed
Project Web Site 08.12.04 10.12.04
Completed
Final Report 10.12.0410.12.04
Completed