This section lists all the resources that will be used during the project lifetime.
Both team members are employed full time for the lifetime of the project:
Name | Hours per Week | Total Hours | |||||||
---|---|---|---|---|---|---|---|---|---|
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
Patric Fornasier | 40 | 40 | 40 | 40 | 40 | 40 | 40 | 40 | 320 |
Pawel Kowalski | 40 | 40 | 40 | 40 | 40 | 40 | 40 | 40 | 320 |
Total | 640 |
We try hard to keep project documentation up-to-date and accessible to everyone. All the documents can be found at any time on the bexee project web site [bexee] .
Activity | Tool |
---|---|
Build Process | Maven |
Development | Eclipse, X-Emacs, UltraEdit |
Documentation | Maven, MS Visio 2003 |
Project Collaboration | SourceForge.net |
Project Planning | MS Project 2003 |
Version Control | CVS |
Item | Nbr |
---|---|
Work station | 2 |